PROJECT DETAILS

Project Submission No. S00307
Project Title İstanbul Wind Power Plant
Project Owner (as per PSF & LOA) Universal Wind Elektrik Üretim A.Ş.
Submission Date 2 Mar 2022
Global Stakeholder Consultation Period 14 Aug 2022 - 28 Aug 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Wind Power
GCC/CDM Methodology & Version ACM0002: “Grid-connected electricity generation from renewable sources” (Version 20.0)
Forecasted GHG Emission Reduction (tCO2e/Year) 453,740 (tCO2e/Year)
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Platinum
Forecasted Market Eligibility CORSIA(C+)
Country Türkiye
Focal Point of Project Owners (FP)
Desilyon Danışmanlık Ticaret A.Ş.
Email of Contact Person of FP (Primary) serkan.korkmaz@desilyon.com.tr
Email of Contact Person of FP (Secondary) ozlem@desilyon.com.tr
Name of Authorized External Representative Organization Desilyon Danışmanlık Ticaret A.Ş.
Name of Focal Point of External Representative Desilyon Danışmanlık Ticaret A.Ş.
Email-id of External representative ozlem@desilyon.com.tr
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

Universal Wind Elektrik Üretim A.Ş. has constructed the İstanbul Wind Power Plant Project. The aim of the project is to produce electrical energy from wind for the Turkish national grid. Universal Wind Elektrik Üretim A.Ş. constructed a wind power plant in Çatalca district, İstanbul province, Turkey. The project activity will generate greenhouse gas (GHG) emission reductions by avoiding CO2 emissions from electricity generation by fossil fuel power plants connected to the Turkish National Power Grid. The total installed capacity is 200 MW. The average annual generated energy is expected to be 700,000 MWh and the project will be able to deliver a reduction in emissions of around 453,740 tCO2e (tons of carbon dioxide equivalent) annually. 