Project Submission No. | S00153 |
---|---|
Project Title | Topçam Dam and Hydro Power Plant |
Project Owner(s) (as per PSF & LOA) | Bilgin Güç Santralleri Enerji Üretim A.Ş. |
Submission Date | 2022-02-22 |
Global Stakeholder Consultation Period |
2022-04-03 to 2022-04-17 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Hydro Power |
GCC/CDM Methodology & Version | ACM0002: “Grid-connected electricity generation from renewable sources” (Version 20.0) |
Forecasted GHG Emission Reduction (tCO2e/Year) | 111,040 |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Platinum |
Forecasted Market Eligibility | C+ - Pilot Phase |
Country |
Türkiye
|
---|---|
Focal Point of Project Owners
|
Bilgin Güç Santralleri Enerji Üretim A.Ş. |
Email of Contact Person of FP (Primary) | altug@bilgin.com.tr |
Email of Contact Person of FP (Secondary) | baharsu.akdag@bilgin.com.tr |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | Bilgin Güç Santralleri Enerji Üretim A.Ş. is operating a hydropower plant in Mesudiye district, Ordu province, Turkey. Based on the applied tool, the project boundary is considered as the National Electricity Grid of Turkey. The baseline scenario refers to the energy generation from the fossil fuels.The project includes 3 units. All of them have 20.87 MWm/ 20.45 MWe installed capacity. The total installed capacity is 62.61 MWm / 61.35 MWe. Annual electricity production is expected to be 200,000,000 kWh according to the generation license. Because of avoiding using fossil fuels, greenhouse gas emission reductions can be achieved. The average annual generated electricity is expected to be 200,000 MWh according to the generation license and the emission reduction is estimated around 111,040 tCO2e annually. |
---|