PROJECT DETAILS

Project Submission No. S00127
Project Title ÇATALTEPE WPP
Project Owner(s) (as per PSF & LOA) 1. SUPER ELEKTRIK URETIM A.Ş., 2. SEKANS ENERJI LIMITED ŞIRKETI
Submission Date 2022-02-15
Global Stakeholder Consultation Period 2022-03-09 to
2022-03-23
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Wind Power
GCC/CDM Methodology & Version CDM Approved AMS-I.D. Grid-connected renewable electricity generation, version 18.0
Forecasted GHG Emission Reduction (tCO2e/Year) 24,538
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Silver
Forecasted Market Eligibility C+ - Pilot Phase
Country
 Türkiye
Focal Point of Project Owners
Sekans Enerji Limited Sirketi
Email of Contact Person of FP (Primary) sila@sekansdanismanlik.com
Email of Contact Person of FP (Secondary) deniz@sekansdanismanlik.com
Name of Authorized External Representative Organization SEKANS ENERJİ LTD.ŞTİ
Name of Focal Point of External Representative SILA DURAN
Email-id of External representative sila@sekansdanismanlik.com
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

Çataltepe WPP (hereafter referred as “Project”) is a new built wind-farm project, located in İstanbul Province, Turkey owned by Süper Elektrik Üretim A.Ş. The generation license of the project was issued in 04/01/2012 for 49 years. The project has an installed capacity of 12 MWm/10 MWe, and annual generation is estimated to be 37,856 MWh.
The purpose of the Project is to produce renewable electricity using wind as the power source and to contribute to Turkey’s growing electricity demand through a sustainable and low carbon technology. The project will displace the same amount of electricity generated by the grid dominated with fossil fired power plants. The annual emission reduction estimated by the project is 24,538 tonnes of CO2. During the crediting period, 245,379 tonnes of CO2 are expected to be reduced.