Project Submission No. S00318
Project Title Solar Power Project by Athena Group
Project Owner (as per PSF & LOA) EKI Energy Services Limited, Athena Jaipur Solar Power Private Limited
Focal Point of Project Owners*(FP)
EKI Energy Services Limited
Email of Contact Person of FP (Primary) manish@enkingint.org
Email of Contact Person of FP (Secondary) naveen@enkingint.org
Country India
Submission Date 15 Feb 2022
Global Stakeholder Consultation Period 22 Aug 2022 - 5 Sep 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
GCC/CDM Methodology & Version ACM0002 Grid-connected electricity generation from renewable sources - Version 20.0
Forecasted GHG Emission Reduction(TCO2/Year) 468,248 tCO2e
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals 1,5,7,8
Forecasted SDG+ Label Platinum
Forecasted Market Eligibility CORSIA(C+)
Name of Authorized External Representative Organization
Name of Focal Point of External Representative
Email-id of Focal Point
Documents for Global Stakeholder Consultation Project Submision, Calculation Sheet, Other Documents
Project Brief

The Project Activity is the installation of a new grid-connected 205 MW Solar power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project is implemented in Karnataka and Rajasthan state of India.
The electricity generated from Project Activity is exported to the Indian grid in India there by displacing electricity from the regional grid electricity distribution system generated by fossil fuel based power plants.
The electricity generated by renewable technology (solar) installed as part of the project activity will be supplied either to the regional grid and/or will be supplied to the identified facility via regional grid through a contractual wheeling agreement for captive consumption there by displacing the
consumption of electricity from the regional grid electricity distribution system. As of 31 December 2013, the Southern grid has also been synchronised with the NEWNE grid, hence forming one unified Indian Grid. Thus for this Project activity instances Indian Grid is applicable
 

Additional Information

The estimated emissions for the project activity is 468,248 tCO2e