| Project Submission No. | S01278 |
|---|---|
| Project Title | Novo Horizonte Wind Project |
| Project Owner(s) (as per PSF & LOA) | Pan American Energy Energias Renovaveis |
| Submission Date | 2024-04-29 |
| Global Stakeholder Consultation Period |
2024-07-31 to 2024-08-14 |
| Registration Date | 2026-03-02 |
| Sector | 1.Energy industries (renewable-/non-renewable sources) |
| Project Type | Wind Power |
| GCC/CDM Methodology & Version | ACM0002 – Grid-connected electricity generation from renewable sources V22.0 |
| Forecasted GHG Emission Reduction (tCO2e/Year) |
|
| Verified GHG Emission Reduction (tCO2e/Year) |
|
| Forecasted E+ Label | Yes |
| Verified E+ Label | Yes |
| Forecasted S+ Label | Yes |
| Verified S+ Label | Yes |
| Forecasted SDG+ Goals |
|
| Verified SDG+ Goals |
|
| Forecasted SDG+ Label | Diamond |
| Verified SDG+ Label | Diamond |
| Forecasted Market Eligibility | C+ - Pilot Phase |
| Verified Market Eligibility |
|
Location Details
Open Full Map
|
|
| Country |
Brazil
|
|---|---|
|
Focal Point of Project Owners
|
Pan American Energy Energias Renovaveis ltda. |
| Email of Contact Person of FP (Primary) | comercialbr@pan-energy.com |
| Email of Contact Person of FP (Secondary) | rrossetto@pan-energy.com |
| Project Verifier | KBS CERTIFICATION SERVICES PVT. LTD. |
| Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
| Request For Registration Documents | Verified Project Submision
Verified Calculation Sheet Other Verified Documents |
| Request for Registration Form | Registration Form |
| Project Brief | The Novo Horizonte Wind Complex consists in the implementation and operation of a new wind electricity generation complex, divided in ten facilities, as follows: Ventos de São Romualdo, Ventos de São Teofano, Ventos de São Teonas, Ventos de São Thomas, Ventos de São Tilão, Ventos de Santo Ubaldo, Ventos de Santo Urbano I, Ventos de São Vigilio, Ventos de Santa Virginia, and Ventos de São Vladimir, located at sites where no major electricity generation facilities existed prior to the implementation of the project activity. The project activity will employ 94 horizontal-axis aerogenerators (model: Vestas V150) each with 4.5 MW, with a total nominal capacity of 423 MW. The facilities Ventos de São Romualdo. Ventos de São Teofano, Ventos de São Teonas, and Ventos de São Vigilio includes 10 aerogenerators each. The facilities Ventos de São Thomas, Ventos de São Tilão, Ventos de Santo Ubaldo, Ventos de Santo Urbano I, Ventos de Santa Virginia, and Ventos de São Vladimir includes 9 aerogenerators. All facilities areas are in the rural area of Ibitiará, Boninal, Oliveira dos Brejinhos and Novo Horizonte municipalities in the State of Bahia, northeast of Brazil
|
|---|
| Report (Public) | Verification Report (public) |
|---|---|
| Verification report date | 2026-01-17 |
| First Request for Registration Date | 2025-07-29 |
| Opinion | KBS was contracted by Pan American Energy Energias Renováveis Ltda on behalf of GCC project owner for verification of the project activity “Novo Horizonte Wind Project” in Brazil. The objectives of this project verification is to validate that the GCC project meets the requirements of GCC project framework v2.1, GCC program manual v3.1, GCC program processes v4.0, GCC project standard v4.0, GCC project sustainability standard v3.1, GCC verification standard v3.1, GCC Environment & Social safeguards standard v3.0, ISO 14064-2 & ISO 14064-3, applicable approved CDM methodology “Grid-connected electricity generation from renewable sources” ACM0002 v22.0, Applicable Legal requirements/rules of host country, National Sustainable Development Criteria and CORSIA requirements and other GCC requirements related to aspects such as project design, applicable conditions, project boundary, baseline scenarios, additionality, emission reduction, monitoring plan, local stakeholder consultation, global stakeholder consultation, GHG emission reductions (ACCs), environmental no-net harm label (E+), social no net harm label (S+), diamond SDG label (SDG+). This report summarizes the final project verification opinion which is based on Project Submission Form v4.0. The Project Activity complies with all the applicable requirement of the GCC Program. The project activity is a wind power project, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved consolidated CDM methodology ACM0002, version 22.0 and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms. The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 604,672 tCO2e/year over the selected fixed 10 years crediting period starting from 01/01/2026. The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. KBS Certification Services Limited (KBS) has verified and hereby certifies that the GCC project activity “Novo Horizonte Wind Project”: a. has correctly described the Project Activity in the Project Submission Form (Version no. 3.1 Dated 07/01/2026) including the applicability of the approved consolidated methodology ACM0002, version 22.0 and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real, measurable and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively; b. is likely to generate GHG emission reductions amounting to the estimated 604,672 tCO2e per year as indicated in the PSF, which are additional to the reductions that are likely to occur in absence of the Project Activity and complies with all applicable GCC rules, including ISO 14064-2 and ISO 14064-3, and therefore requests the GCC Program to register the Project Activity; c. is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+) and the Social No- net-harm Label (S+). The project level impacts are identified in the PSF for the Environmental and Social Safeguarding with E+ score as +6 and S+ score as +5; and d. is likely to contribute to the achievement of United Nations Sustainable Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 7 SDGs, which is likely to achieve the Diamond SDG certification label (SDG+). |