| Project Submission No. | S01257 |
|---|---|
| Project Title | Fuel Efficiency Improvement for Al Walidia Power Plant in Egypt |
| Project Owner(s) (as per PSF & LOA) | EKI Energy Services Limited |
| Submission Date | 2024-04-15 |
| Global Stakeholder Consultation Period |
2024-06-23 to 2024-07-07 |
| Sector | 1.Energy industries (renewable-/non-renewable sources) |
| Project Type | EE Measures |
| GCC/CDM Methodology & Version | AM0061 - Methodology for rehabilitation and/or energy efficiency improvement in existing power plants - Version 2.1 |
| Forecasted GHG Emission Reduction (tCO2e/Year) |
|
| Forecasted E+ Label | Yes |
| Forecasted S+ Label | Yes |
| Forecasted SDG+ Goals |
|
| Forecasted SDG+ Label | Silver |
| Forecasted Market Eligibility | C+ - Pilot Phase |
|
Location Details
Open Full Map
|
|
| Country |
Egypt
|
|---|---|
|
Focal Point of Project Owners
|
EKI Energy Services Limited |
| Email of Contact Person of FP (Primary) | manish@enkingint.org |
| Email of Contact Person of FP (Secondary) | naveen@enkingint.org |
| Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
| Project Brief | The project activity is the fuel efficiency improvement in Al-Walidia thermal power plant in Assiut, Egypt by implementing rehabilitation measures to improve energy efficiency. The baseline scenario of the Project is continuation of the existing scenario, i.e. operating the existing Al Walidia power plant, continuing to use all power generation equipment that was already in use prior to the implementation of the project activity and undertaking business as usual maintenance. |
|---|---|
| Additional Information | The annual emission calculation for this project activity is 123,136 TCO2e. |