PROJECT DETAILS

Project Submission No. S00008
Project Title 70 MW Renewable Solar Power Project by Jakson Power Private Limited
Project Owner (as per PSF) Jakson Power Private Limited, EKI Energy Services Limited (focal point to act on behalf of all Project Owners)
Contact Person of Project Owner EKI Energy Services Limited
Email of Contact Person of PO (Primary) supratik@enkingint.org
Email of Contact Person of PO (Secondary) manish@enkingint.org
Country India
Submission Date 5 Jun 2021
Global Stakeholder Consultation Period 15 Jul 2021 - 29 Jul 2021
Sector 1.Energy industries (renewable-/non-renewable sources)
GCC/CDM Methodology & Version ACM0002 Grid-connected electricity generation from renewable sources --- Version 20.0 (Approved CDM methodology)
Forecasted GHG Emission Reduction(TCO2/Year) 106,437
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals 1,5,7,8,9,11,13
Forecasted SDG+ Label Diamond
Forecasted Market Eligibility CORSIA(C+)
Name of Authorized External Representative Organization
Name of Focal Point of External Representative
Email-id of Focal Point
Documents for Global Stakeholder Consultation Project Submision, Calculation Sheet, Other Documents
Project Brief

The proposed Project Activity is the installation of a new grid-connected 70 MW solar power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project is being implemented in Assam state of India by Jakson Power Private Limited.
The electricity generated from Project Activity will be exported to the Indian grid in India there by displacing the consumption of electricity from the regional grid electricity distribution system.
The electricity generated by the Project Activity thus will replace the equivalent amount of electricity generated by the operation of existing/ grid connected power plants (mostly fossil fuel based power plants) and by addition of new generation sources into the grid. The Project Activity thus reduces the anthropogenic emissions of greenhouse gases (GHGs) in to the atmosphere associated with the equivalent amount of electricity generation from the existing grid connected power plants (mostly fossil fuel) and by addition of new generation sources into the grid.

Additional Information

Jakson Power Private Limited is Project Implementer. The annual estimated emission reductions over crediting period is 106,437 tCO2e/annum.