IMPORTANT UPDATE: We are migrating to GCC 2.0. We have restricted new projects registration and further updates to migrated project. Please visit to GCC 2.0.

PROJECT DETAILS

Project Submission No. S01208
Project Title SOCAR-1 Hydro Bundle
Project Owner(s) (as per PSF & LOA) 1. “Azerenerji” Open Joint-Stock Company 2. SOCAR Trading SA
Submission Date 2024-01-09
Global Stakeholder Consultation Period 2024-04-16 to
2024-04-30
Registration Date 2026-07-14
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Hydro Power
GCC/CDM Methodology & Version AMS-I.D: Grid connected renewable electricity generation, Version 18.0
Forecasted GHG Emission Reduction (tCO2e/Year) 18,382
Verified GHG Emission Reduction (tCO2e/Year) 18,382
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Silver
Verified SDG+ Label Silver
Forecasted Market Eligibility C+ - Pilot Phase
Verified Market Eligibility
Location Details Open Full Map
Country
 Azerbaijan
Focal Point of Project Owners
SOCAR Trading SA
Email of Contact Person of FP (Primary) jnoller@socartrading.com
Email of Contact Person of FP (Secondary) amuradylova@socartrading.com
Project Verifier Earthood Services Private Limited
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Request For Registration Documents Verified Project Submision
Verified Calculation Sheet

Other Verified Documents
Request for Registration Form Registration Form
Project Brief

SOCAR-1 Hydro Bundle is a bundled project which is implemented by “Azerenerji” Open Joint-Stock Company. The project is reducing national energy deficit and development of local industries as it allows the use of local sources for energy generation.

The purpose of the project is to generate clean energy by harnessing the hydro power and providing the energy to the Azerbaijan national grid. By implementing the project, investors also aim to reduce dependency to the fossil fuels thereby reducing the sources of environmental pollution.

In this scope, the project owner installed hydropower plants with the purpose of contributing to the national economy by meeting the increased electricity demand. Total output of the plant will be limited at 13.6 MWe. Chirag-1 and Soyugbulag are located on Tartar River, Kalbajar District, Baku Province. The project activity will generate greenhouse gas (GHG) emission reductions by avoiding CO2e emissions from electricity generation by fossil fuel power plants connected to Azerbaijani National Power Grid.

VERIFICATION OUTCOME
Report (Public) Verification Report (public)
Verification report date 2026-06-12
First Request for Registration Date 2024-10-18
Opinion

<!-- /* Style Definitions */ p.MsoNormal, li.MsoNormal, div.MsoNormal {mso-style-priority:1; mso-style-unhide:no; mso-style-qformat:yes; mso-style-parent:""; margin:0cm; mso-pagination:none; text-autospace:none; font-size:10.0pt; mso-bidi-font-size:11.0pt; font-family:"Arial",sans-serif; mso-fareast-font-family:PFDinTextUniversal-Light; mso-bidi-font-family:PFDinTextUniversal-Light; mso-ansi-language:EN-US; mso-fareast-language:EN-US;} p.SDMTableBoxParaNotNumbered, li.SDMTableBoxParaNotNumbered, div.SDMTableBoxParaNotNumbered {mso-style-name:SDMTable&BoxParaNotNumbered; mso-style-unhide:no; mso-style-qformat:yes; margin:0cm; mso-pagination:widow-orphan; font-size:10.0pt; font-family:"Arial",sans-serif; mso-fareast-font-family:"Times New Roman"; mso-bidi-font-family:"Times New Roman"; mso-ansi-language:EN-GB; mso-fareast-language:DE;} p.Default, li.Default, div.Default {mso-style-name:Default; mso-style-unhide:no; mso-style-parent:""; margin:0cm; mso-pagination:widow-orphan; mso-layout-grid-align:none; text-autospace:none; font-size:12.0pt; font-family:"Arial",sans-serif; mso-fareast-font-family:Calibri; mso-fareast-theme-font:minor-latin; color:black; mso-fareast-language:EN-US;} .MsoChpDefault {mso-style-type:export-only; mso-default-props:yes; font-size:11.0pt; mso-ansi-font-size:11.0pt; mso-bidi-font-size:11.0pt; font-family:"Calibri",sans-serif; mso-ascii-font-family:Calibri; mso-ascii-theme-font:minor-latin; mso-fareast-font-family:Calibri; mso-fareast-theme-font:minor-latin; mso-hansi-font-family:Calibri; mso-hansi-theme-font:minor-latin; mso-bidi-font-family:Arial; mso-bidi-theme-font:minor-bidi; mso-font-kerning:0pt; mso-ligatures:none; mso-ansi-language:EN-US; mso-fareast-language:EN-US;} .MsoPapDefault {mso-style-type:export-only; mso-pagination:none; text-autospace:none;} @page WordSection1 {size:612.0pt 792.0pt; margin:72.0pt 72.0pt 72.0pt 72.0pt; mso-header-margin:36.0pt; mso-footer-margin:36.0pt; mso-paper-source:0;} div.WordSection1 {page:WordSection1;} /* List Definitions */ @list l0 {mso-list-id:377124645; mso-list-type:hybrid; mso-list-template-ids:870205414 -1429862982 134807577 134807579 134807567 134807577 134807579 134807567 134807577 134807579;} @list l0:level1 {mso-level-number-format:alpha-lower; mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt; mso-ansi-font-size:10.0pt; mso-bidi-font-size:10.0pt;} @list l0:level2 {mso-level-number-format:alpha-lower; mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt;} @list l0:level3 {mso-level-number-format:roman-lower; mso-level-tab-stop:none; mso-level-number-position:right; text-indent:-9.0pt;} @list l0:level4 {mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt;} @list l0:level5 {mso-level-number-format:alpha-lower; mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt;} @list l0:level6 {mso-level-number-format:roman-lower; mso-level-tab-stop:none; mso-level-number-position:right; text-indent:-9.0pt;} @list l0:level7 {mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt;} @list l0:level8 {mso-level-number-format:alpha-lower; mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt;} @list l0:level9 {mso-level-number-format:roman-lower; mso-level-tab-stop:none; mso-level-number-position:right; text-indent:-9.0pt;} -->

<!-- /* Style Definitions */ p.MsoNormal, li.MsoNormal, div.MsoNormal {mso-style-priority:1; mso-style-unhide:no; mso-style-qformat:yes; mso-style-parent:""; margin:0cm; mso-pagination:none; text-autospace:none; font-size:10.0pt; mso-bidi-font-size:11.0pt; font-family:"Arial",sans-serif; mso-fareast-font-family:PFDinTextUniversal-Light; mso-bidi-font-family:PFDinTextUniversal-Light; mso-ansi-language:EN-US; mso-fareast-language:EN-US;} p.SDMTableBoxParaNotNumbered, li.SDMTableBoxParaNotNumbered, div.SDMTableBoxParaNotNumbered {mso-style-name:SDMTable&BoxParaNotNumbered; mso-style-unhide:no; mso-style-qformat:yes; margin:0cm; mso-pagination:widow-orphan; font-size:10.0pt; font-family:"Arial",sans-serif; mso-fareast-font-family:"Times New Roman"; mso-bidi-font-family:"Times New Roman"; mso-ansi-language:EN-GB; mso-fareast-language:DE;} p.Default, li.Default, div.Default {mso-style-name:Default; mso-style-unhide:no; mso-style-parent:""; margin:0cm; mso-pagination:widow-orphan; mso-layout-grid-align:none; text-autospace:none; font-size:12.0pt; font-family:"Arial",sans-serif; mso-fareast-font-family:Calibri; mso-fareast-theme-font:minor-latin; color:black; mso-fareast-language:EN-US;} .MsoChpDefault {mso-style-type:export-only; mso-default-props:yes; font-size:11.0pt; mso-ansi-font-size:11.0pt; mso-bidi-font-size:11.0pt; font-family:"Calibri",sans-serif; mso-ascii-font-family:Calibri; mso-ascii-theme-font:minor-latin; mso-fareast-font-family:Calibri; mso-fareast-theme-font:minor-latin; mso-hansi-font-family:Calibri; mso-hansi-theme-font:minor-latin; mso-bidi-font-family:Arial; mso-bidi-theme-font:minor-bidi; mso-font-kerning:0pt; mso-ligatures:none; mso-ansi-language:EN-US; mso-fareast-language:EN-US;} .MsoPapDefault {mso-style-type:export-only; mso-pagination:none; text-autospace:none;} @page WordSection1 {size:612.0pt 792.0pt; margin:72.0pt 72.0pt 72.0pt 72.0pt; mso-header-margin:36.0pt; mso-footer-margin:36.0pt; mso-paper-source:0;} div.WordSection1 {page:WordSection1;} /* List Definitions */ @list l0 {mso-list-id:377124645; mso-list-type:hybrid; mso-list-template-ids:870205414 -1429862982 134807577 134807579 134807567 134807577 134807579 134807567 134807577 134807579;} @list l0:level1 {mso-level-number-format:alpha-lower; mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt; mso-ansi-font-size:10.0pt; mso-bidi-font-size:10.0pt;} @list l0:level2 {mso-level-number-format:alpha-lower; mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt;} @list l0:level3 {mso-level-number-format:roman-lower; mso-level-tab-stop:none; mso-level-number-position:right; text-indent:-9.0pt;} @list l0:level4 {mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt;} @list l0:level5 {mso-level-number-format:alpha-lower; mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt;} @list l0:level6 {mso-level-number-format:roman-lower; mso-level-tab-stop:none; mso-level-number-position:right; text-indent:-9.0pt;} @list l0:level7 {mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt;} @list l0:level8 {mso-level-number-format:alpha-lower; mso-level-tab-stop:none; mso-level-number-position:left; text-indent:-18.0pt;} @list l0:level9 {mso-level-number-format:roman-lower; mso-level-tab-stop:none; mso-level-number-position:right; text-indent:-9.0pt;} -->

Earthood is contracted by SOCAR Trading SA. for project verification of the project activity “SOCAR-1 Hydro Bundle” in Azerbaijan. The project verification was performed based on rules and requirements defined by GCC for the project activity.

The project activity is a bundle hydro power project, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the Approved CDM Baseline and Monitoring AMS.I.D. Version 18.0/19/ including applicable CDM Tools and is assessed against latest valid GCC Project Standard/04/, Verification Standard/05/, Environment and Social Safeguards Standard/07/, Project-Sustainability-Standard/06/ and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms/clarifications.

The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 183,820 tCO2e over the 10 years crediting period starting from 01/01/2026.  

ESPL has informed the project owners of the verification outcome through the draft verification report and final verification report. The final verification report contains the information with regard to fulfilment of the requirements for verification, as appropriate.

Earthood Services Private Limited (ESPL) has verified and hereby certifies that the GCC project activity “SOCAR-1 Hydro Bundle”

a.     has correctly described the Project Activity in the Project Submission Form (version 14.0 dated: 11/06/2026) including the applicability of the approved CDM methodology AMS.I.D. Version 18.0/19/  and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively;

b.     is likely to generate GHG emission reductions amounting to the estimated 18,382 tCO2e per year as indicated in the PSF, which are additional to the reductions that are likely to occur in absence of the Project Activity and complies with all applicable GCC rules, including ISO 14064-2 and ISO 14064-3, and therefore requests the GCC Program to register the Project Activity;

c.     is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard. the project level impacts are identified in the PSF for the Environmental and Social Safeguarding with E+ score as 6 and S+ score as 5. Adequate monitoring system is defined and is in-place to monitor these impacts throughout the crediting period. and therefore, requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+) and the Social No-net-harm Label (S+); and

d.     is likely to contribute to the achievement of United Nations Sustainable Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 3 SDGs, which is likely to achieve the Silver SDG certification label (SDG+). The project level SDG indicators are defined for each SDG contribution and there is a system in-place to monitor and verify the contribution throughout the crediting period.

e.     The Project Activity complies with all the applicable requirement of the GCC Program and ICAO’s requirements on CORSIA Emissions Unit Eligibility Criteria and CORSIA Eligible Emissions Units, as per Clarification No 1., v1.3/08/ paragraph 23-25, and the ACCs expected to be issued during the crediting period is likely to be CORSIA eligible and can be used by International Airlines for offsetting their emissions during all phases of CORSIA and therefore requests GCC Steering Committee to append CORSIA Certification label (C+) to this project. The written attestation from the Host country on double counting shall be submitted by the project owner at ACCs issuance stage (A FAR (FAR#01) remains open regarding the same).

Therefore, the project is being recommended to GCC Steering Committee for request for registration.

© 2026 Global Carbon Council