| Project Submission No. | S01110 |
|---|---|
| Project Title | Beaskund Top Hydro Power Project by Gopal Hydrogen Private Limited |
| Project Owner(s) (as per PSF & LOA) | Gopal Hydrogen Private Limited ; EKI Energy Services Limited |
| Submission Date | 2023-09-08 |
| Global Stakeholder Consultation Period |
2024-01-04 to 2024-01-18 |
| Sector | 1.Energy industries (renewable-/non-renewable sources) |
| Project Type | Hydro Power |
| GCC/CDM Methodology & Version | AMS-I.D.: Grid connected renewable electricity generation --- Version 18.0 |
| Forecasted GHG Emission Reduction (tCO2e/Year) |
|
| Forecasted E+ Label | Yes |
| Forecasted S+ Label | Yes |
| Forecasted SDG+ Goals |
|
| Forecasted SDG+ Label | Silver |
| Forecasted Market Eligibility | C+ - Pilot Phase |
|
Location Details
Open Full Map
|
|
| Country |
India
|
|---|---|
|
Focal Point of Project Owners
|
EKI Energy Services Limited |
| Email of Contact Person of FP (Primary) | manish@enkingint.org |
| Email of Contact Person of FP (Secondary) | naveen@enkingint.org |
| Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
| Project Brief | The Project Activity is the installation of a new grid-connected 4.9 MW small hydro power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project is implemented in Himachal Pradesh, India by Gopal Hydrogen Private Limited. The electricity generated from Project Activity is exported to the Indian grid in India there by displacing electricity from the regional grid electricity distribution system generated by fossil fuel based power plants. |
|---|---|
| Additional Information | The annual emission calculation for this project activity is 21796 TCO2e. |