PROJECT DETAILS

Project Submission No. S01096
Project Title Wind project by Juniper Green Beam Private Limited in Gujarat
Project Owner(s) (as per PSF & LOA) Juniper Green Energy Private Limited, Juniper Green Beam Private Limited
Submission Date 2023-07-31
Global Stakeholder Consultation Period 2023-12-19 to
2024-01-02
Registration Date 2026-03-31
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Wind Power
GCC/CDM Methodology & Version ACM0002 Version 21.0
Forecasted GHG Emission Reduction (tCO2e/Year) 230,384
Verified GHG Emission Reduction (tCO2e/Year) 230,384
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Silver
Verified SDG+ Label Silver
Forecasted Market Eligibility C+ - Pilot Phase
Verified Market Eligibility
Location Details Open Full Map
Country
 India
Focal Point of Project Owners
Juniper Green Energy Private Limited
Email of Contact Person of FP (Primary) ankush.malik@junipergreenenergy.com
Email of Contact Person of FP (Secondary) pavan.gupta@junipergreenenergy.com
Project Verifier Enviance Services Private Limited
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Request For Registration Documents Verified Project Submision
Verified Calculation Sheet

Other Verified Documents
Request for Registration Form Registration Form
Project Brief

The proposed project activity is the installation of a new grid-connected 69.3 MW wind power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project activity is wind power project which is being implemented in Villages Adala, Dhandalpur, Navagam, Pipaliya, Kaswali, Kotda, and other villages in Sayla Taluk, Surendra Nagar District, Gujarat of India by Juniper Green Beam Private Limited. The electricity generated from Project Activity is exported to the Indian grid there by displacing the consumption of electricity from the regional grid electricity distribution system.

And by the addition of new generation sources into the grid “Wind project by Juniper Green Beam Private Limited in Gujarat” will thus replace the equivalent amount of electricity generated by the operation of existing grid connected power plants (mostly fossil fuel-based power plants). In this scope, Juniper Green Beam Private Limited planned to install 22 WTG x 3.15 MW wind turbines in with the purpose of contributing to the national economy. The estimated annual average electricity generation by the project activity is 246,348.19 MWh.

The crediting period chosen for the project activity “Wind project by Juniper Green Beam Private Limited in Gujarat” is 10 years Crediting Period for which total estimated electricity generation is 2463481.94 MWh and emission reduction are 2,303,840 tCO2. The annual estimated emission reductions from project activity are 230,384 tCO2e/annum.

Additional Information

The proposed project activity is the installation of a new grid-connected 69.3 MW wind power plant. The project activity is wind power project which is being implemented in Villages Adala, Dhandalpur, Navagam, Pipaliya, Kaswali, Kotda, and other villages in Sayla Taluk, Surendra Nagar District, Gujarat of India.

VERIFICATION OUTCOME
Report (Public) Verification Report (public)
Verification report date 2026-03-25
First Request for Registration Date 2024-03-21
Opinion

Enviance Services Private Limited has performed a verification of the “Wind project by Juniper Green Beam Private Limited in Gujarat”. The verification is performed on the basis of GCC criteria Project Verification Standard, Version 3.1 for the project activity, GCC guideline and host country criteria, as well as criteria given to provide for consistent project operations, monitoring and reporting.

The review of the final version of GCC PSF and the subsequent Onsite Visit / follow-up interviews has provided Enviance Services Private Limited with sufficient evidence to determine the fulfilment of stated criteria. In our opinion, the project meets all relevant GCC project standard requirements for the GCC. The project will hence be recommended by Enviance Services Private Limited for registration with the GCC.

By displacing fossil fuel-based electricity with electricity generated from a renewable source, the project results in reductions of CO2 emissions that are real, measurable and give long-term benefits to the mitigation of climate change. Emission reductions attributable to the project are hence additional to any that would occur in the absence of the project activity. Given that the project is implemented as designed, the project is likely to achieve the estimated amount of annual emission reductions of 230,384 tCO2 equivalent per year.

The verification has been performed following the requirements of the latest version of GCC verification standard, Version 03.1, GCC Project Standard, version 03.1 and on the basis of the contractual agreement.

In detail the conclusions can be summarized as follows:

-     The project does not result in negative social, environmental and/or economic impacts.

-     The project contribution to Environment, Social Development and Economic and technological development

-     The project additionality is sufficiently justified in the GCC PSF

-     Conservative assumptions were applied in the project description.

-     The monitoring plan of SDG parameters is transparent and adequate.

-     The project meets the local stakeholder consultation requirements.

-        The project is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+) and the Social No-net-harm Label (S+); and

-        The project is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 3 SDGs (7, 8, and 13), which is likely to achieve the gold SDG certification label (SDG+)

-        The Project Activity complies with all the applicable requirement of the GCC Program and Global Carbon Council Project Verification Report 40 of 64 ICAO’s requirements on CORSIA Emissions Unit Eligibility Criteria and CORSIA Eligible Emissions Units, as per Clarification No 1., v1.3 paragraph 23-25, and the ACCs expected to be issued during the crediting period is likely to be CORSIA eligible and can be used by International Airlines for offsetting their emissions during all phases of CORSIA and therefore requests GCC Steering Committee to append CORSIA Certification label (C+) to this project. The written attestation from the Host country on double counting shall be submitted by the project owner at ACCs issuance stage. A FAR remains open regarding the same.

The conclusions of this report show, that the project, as it was described in the project documentation, is in line with all criteria applicable for the verification.