| Project Submission No. | S01046 |
|---|---|
| Project Title | Umutlu HEPP |
| Project Owner(s) (as per PSF & LOA) | -GA Elektrik Enerjisik Üretim Satış Sanayi ve Ticaret A.Ş. -GTE KARBON SÜRDÜRÜLEBİLİR ENERJİ EĞİTİM DANIŞMANLIK VE TİCARET A.Ş. |
| Submission Date | 2023-06-22 |
| Global Stakeholder Consultation Period |
2023-10-01 to 2023-10-15 |
| Registration Date | 2026-07-09 |
| Sector | 1.Energy industries (renewable-/non-renewable sources) |
| Project Type | Hydro Power |
| GCC/CDM Methodology & Version | ACM0002 “Grid-connected electricity generation from renewable sources”, Version 21.0 |
| Forecasted GHG Emission Reduction (tCO2e/Year) |
|
| Verified GHG Emission Reduction (tCO2e/Year) |
|
| Forecasted E+ Label | Yes |
| Verified E+ Label | Yes |
| Forecasted S+ Label | Yes |
| Verified S+ Label | Yes |
| Forecasted SDG+ Goals |
|
| Verified SDG+ Goals |
|
| Forecasted SDG+ Label | Silver |
| Verified SDG+ Label | Silver |
| Forecasted Market Eligibility | C+ - Pilot Phase |
| Verified Market Eligibility | C+ - Pilot Phase |
|
Location Details
Open Full Map
|
|
| Country |
Türkiye
|
|---|---|
|
Focal Point of Project Owners
|
GTE KARBON SÜRDÜRÜLEBİLİR ENERJİ EĞİTİM DAN VE TIC A.S |
| Email of Contact Person of FP (Primary) | kemal.demirkol@gte.com.tr |
| Email of Contact Person of FP (Secondary) | beste.dingil@gte.com.tr |
| Name of Authorized External Representative Organization | - |
| Name of Focal Point of External Representative | - |
| Email-id of External representative | kemal.demirkol@gte.com.tr |
| Project Verifier | Carbon Check (India) Private Limited |
| Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
| Request For Registration Documents | Verified Project Submision
Verified Calculation Sheet Other Verified Documents |
| Request for Registration Form | Registration Form |
| Project Brief | Umutlu HEPP which is a run of river type project on the Yeşilırmak River in Taşova district in Amasya Province, has been developed by GA Elektrik Enerjisi Üretim Satış Sanayi ve Ticaret A.Ş. The project aims to contribute to reducing national energy deficit and development of local industries as it allows the use of cheaper energy for industrialists and gain advantage in a competitive environment. GA Elektrik Enerjisi Üretim Satış Sanayi ve Ticaret A.Ş. has the legal ownership of the ACCs generated by this project activity as per LoA. |
|---|
| Report (Public) | Verification Report (public) |
|---|---|
| Verification report date | 2026-06-08 |
| First Request for Registration Date | 2024-05-03 |
| Opinion | Carbon Check was contracted by GA ELEKTRIK ENERJISI ÜRETIM SATIŞ SANAYI VE TICARET A.Ş.for project verification of the project activity “UMUTLU HEPP” in Türkiye. The project verification was performed based on rules and requirements defined by GCC for the project activity. The project activity is a hydro power project, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved baseline and monitoring ACM0002 version 21.0 and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard, Project-Sustainability-Standard and/or The project does not meet the requirements of the CORSIA Eligible Emissions Units required for GCC projects. The start date of the crediting period is 08/04/2016, which is after the date of 1 January 2016. However, since the installed capacity of the project activity is higher than 15 MWe (20.34 MWe as per the generation license), the PO does not intend to use for CORSIA. And the project is likely to:
|