IMPORTANT UPDATE: We are migrating to GCC 2.0. We have restricted new projects registration and further updates to migrated project. Please visit to GCC 2.0.

PROJECT DETAILS

Project Submission No. S00921
Project Title Xitieshan Liushaping 49.5MW Wind Power Project
Project Owner(s) (as per PSF & LOA) Climate Bridge (Shanghai) Ltd.
Submission Date 2023-02-01
Global Stakeholder Consultation Period 2023-03-09 to
2023-03-23
Registration Date 2024-09-04
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Wind Power
GCC/CDM Methodology & Version ACM0002 version21.0
Forecasted GHG Emission Reduction (tCO2e/Year) 69,530
Verified GHG Emission Reduction (tCO2e/Year) 69,530
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Silver
Verified SDG+ Label Silver
Forecasted Market Eligibility C+ - Pilot Phase
Verified Market Eligibility C+ - Pilot Phase
Location Details Open Full Map
Country
 China
Focal Point of Project Owners
Climate Bridge (Shanghai) Ltd.
Email of Contact Person of FP (Primary) projects@climatebridge.com
Email of Contact Person of FP (Secondary) huang.shanfeng@climatebridge.com
Project Verifier Verico SCE
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Request For Registration Documents Verified Project Submision
Verified Calculation Sheet

Other Verified Documents
Request for Registration Form Registration Form
Project Brief

Xitieshan Liushaping 49.5MW Wind Power Project is a wind power project with total installed capacity of 49.5MW. Project is invested and operated by Three Gorges New Energy Dachaidan Wind Power Co., Ltd. The project locates in Xitieshan Town, Dachaidan Administrative District, Haixi Prefecture, Qinghai Province in P.R. China. The project is a renewable energy project and is expected to supply an annual average of 89,221.5 MWh of zero-emission electricity to NWCPG during the fixed 10-year crediting period, which will replace power generation of those fossil fuel-fired power plants delivered to the NWCPG under the baseline scenario. The project is expected to achieve a green-house gas emission reduction of 69,530 tCO2e annually. The total emission reductions during the fixed 10-year crediting period will be 695,300 tCO2e.

VERIFICATION OUTCOME
Report (Public) Verification Report (public)
Verification report date 2024-08-16
First Request for Registration Date 2023-08-08
Opinion

Verico SCE has undertaken the verification of the proposed project «Xitieshan Liushaping 49.5MW Wind Power Project » in P.R.China to be implemented by the Project Legal Owner
“ Three Gorges New Energy Dachaidan Wind Power Co.,Ltd” based on the requirements defined by GCC program for the project activity, and other rules applicable to the project
verification including the host country’s legislation and its specific requirements for sustainable development.


The purpose of the project is to build a 49.5MW wind farm which results in reductions of GHG emissions of 69,530 tCO2e annually during the fixed 10 year crediting period to replace the
electricity generated by fossil fuel dominated power grid in the host country. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the
project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved baseline and monitoring ACM0002 Version 21.0 and is
assessed against latest valid Project Standard, Verification Standard and Environment and Social Safeguards Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance.


To arrive at the final verification conclusions and opinion, verico SCE carried out desk reviews, background investigations and a web audit, taking into account the sustainable
development related regulations/laws in the host country and specific GCC rules/requirements, as well as applicable GCC standards, in particular the approved methodology ACM0002, Version 21.0.


Through the project verification process, the verification team identified eight (8) corrective action requests, eleven (11) clarification requests and one (1) forward action request. The
Project Owner has taken actions to address the findings and submitted to verico SCE several sets of project document revisions resulting in a final Project Submission Form, Version 2.0
dated 21 December 2023 substantiated by supporting evidence. All findings have been appropriately closed before the issuance of this verification statement.


The verification team is of the opinion that the GCC project: «Xitieshan Liushaping 49.5MW Wind Power Project» with the verified final version of Project Submission Form:


a. is in accordance with all the relevant GCC program requirements as well as the host country’s national requirements and if implemented as designed, is likely to achieve the
verified emission reduction estimations of 69,530 tCO2e annually, following the monitoring provisions fixed in the final documentation;


b. is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard, and therefore requests the GCC
Program to register the Project Activity, which is likely to achieve the requirements of the Environmental No-net-harm Label (E+ ) and the Social No-net-harm Label (S+ ); and


c. is likely to contribute to the achievement of United Nations Sustainable Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving
a total of 3 SDGs (7,8 and 13), which is likely to achieve the Silver SDG certification label (SDG+).


The project meets all of the GCC Rules and criteria for CORSIA and project owner has clarified the intent of use of carbon credits for the pilot phase of CORSIA hence for carbon credits issued generated during 01/01/2016 to 31/12/2020, HCA is not required for CORSIA labelled credits.


Therefore, verico SCE hereby certifies that the Project Submission Form Version 2.0 dated 21 December 2023 of the proposed GCC project «Xitieshan Liushaping 49.5MW Wind Power Project » is in accordance with the above stated requirements.

© 2025 Global Carbon Council