Project Submission No. | S00052 |
---|---|
Project Title | 55.3 MW bundled wind power project by Atria Power in India |
Project Owner(s) (as per PSF & LOA) | 1. Atria Wind Power (Bijapur2) Pvt. Ltd., 2. Atria Wind Power (Savarakundla) Pvt. Ltd. |
Submission Date | 2021-05-03 |
Global Stakeholder Consultation Period |
2021-12-21 to 2022-01-04 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Wind Power |
GCC/CDM Methodology & Version | ACM0002 Grid-connected electricity generation from renewable sources, Version 20.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) | 137,127 |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Gold |
Forecasted Market Eligibility | C+ - Pilot Phase |
Country |
India
|
---|---|
Focal Point of Project Owners
|
Kosher Climate India Private Limited |
Email of Contact Person of FP (Primary) | narendra@kosherclimate.com |
Email of Contact Person of FP (Secondary) | info@atriapower.com |
Name of Authorized External Representative Organization | Kosher Climate India Private Limited |
Name of Focal Point of External Representative | Vamsi Krishna M |
Email-id of External representative | vamsi@kosherclimate.com |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | The bundled project activity involves installation of two wind power projects of capacities 23.3 MW, 32 MW each in the states of Karnataka and Gujarat states of India respectively. Both the projects are commissioned and operational. Both the project has been connected to the National Grid through the locally available distribution substations. Generated power from project 1 and project 2 is being supplied to the government distribution companies under long-term power purchase agreements. The wind power projects are promoted by subsidiaries of Atria Group. The renewable electricity generated from the project is supplied to the grid and thereby replacing the equivalent amount of electricity from the grid which is mainly dominated by thermal/fossil fuel-based power plants. Hence the project will reduce the associated CO2 emission from the grid-connected power plants. |
---|