Project Submission No. | S00859 |
---|---|
Project Title | Solar Power Project by Perinyx Neep Private Limited |
Project Owner (as per PSF & LOA) | EKI Energy Services Limited |
Submission Date | 29 Jul 2022 |
Global Stakeholder Consultation Period | 1 Feb 2023 - 15 Feb 2023 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | AMS-I.D.: Grid connected renewable electricity generation - Version 18.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) | 12,110 (tCO2e/Year) |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
Forecasted SDG+ Goals | |
Forecasted SDG+ Label | Platinum |
Forecasted Market Eligibility | CORSIA(C+) |
Country | India |
---|---|
Focal Point of Project Owners (FP)
|
EKI Energy Services Limited |
Email of Contact Person of FP (Primary) | manish@enkingint.org |
Email of Contact Person of FP (Secondary) | naveen@enkingint.org |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Project Brief | The proposed Project Activity is the installation of a new 8 MW solar power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (greenfield plant). The project is being implemented in Tamil Nadu State of India by Perinyx Neep Private |
---|---|
Additional Information | The annaul estimated emission reductions for the project activity is 12,110 tCO2e. The project is being submitted as A3 type project. |