PROJECT DETAILS

Project Submission No. S00857
Project Title Renewable Solar Power Project by Phelan Energy India RJ Private Limited.
Project Owner (as per PSF & LOA) Phelan Energy India RJ Private Limited.
Submission Date 18 Jul 2022
Global Stakeholder Consultation Period 30 Jan 2023 - 13 Feb 2023
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version CDM approved consolidated Methodology ACM0002 (Version 21.0)
Forecasted GHG Emission Reduction (tCO2e/Year) 112,250 (tCO2e/Year)
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Silver
Forecasted Market Eligibility CORSIA(C+)
Location Details Open Full Map
Country India
Focal Point of Project Owners (FP)
EKI Energy Services Limited
Email of Contact Person of FP (Primary) manish@enkingint.org
Email of Contact Person of FP (Secondary) carbon@ayanapower.com
Name of Authorized External Representative Organization EKI Energy Services Limited
Name of Focal Point of External Representative Mr. Manish Dabkara
Email-id of External representative manish@enkingint.org
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

The project activity is a new grid-connected 50 MW (AC) (70 MWp)solar power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project is implemented in Rajasthan state of India by Phelan Energy India RJ Private Limited.

Additional Information

The annual estimated GHG emission reductions from project activity is 112,250 tCO2e.

This Project is being submitted for RE-Global Stakeholder Consultation.

 

VERIFICATION OUTCOME
Opinion

ESPL was contracted by EKI Energy Services Limited for verification of the project activity “Renewable Solar Power Project by Phelan Energy India RJ Private Limited” in India. The verification was performed based on rules and requirements defined by GCC program for the project activity.

 

The project activity is a solar power project, which results in reductions of CO2 emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved baseline and monitoring ACM0002 version 21.0 and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms.

 

The Project Activity complies with all the applicable requirement of the GCC Program and ICAO’s requirements on CORSIA Emissions Unit Eligibility Criteria and CORSIA Eligible Emissions Units, as per Clarification No 1, paragraph 21-23, and the ACCs expected to be issued during the crediting period is likely to be CORSIA eligible and can be used by International Airlines for offsetting their emissions during all phases of CORSIA and therefore requests GCC Steering Committee to append CORSIA Certification label (C+) to this prroject

 

The project activity is likely to achieve the anticipated emission reductions stated in the PSF /07/ provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 112,250 tCO2e/year over the selected Fixed 10 years crediting period starting from 06/11/2018. The project activity is likely to achieve the anticipated emission reductions stated in the PSF /07/ provided the underlying assumptions do not change. ESPL has informed the project owners of the verification outcome through the draft verification report and final verification report. The final verification report contains the information with regard to fulfilment of the requirements for verification, as appropriate. ESPL applied the following verification process and methodology using a competent verification team;

 

·       The desk review of documents and evidences submitted by the project participant in context of the reference GCC rules and guidelines issued

·       Undertaking/conducting site visit, interview or interactions with the representative of the project participant

·       Reporting audit findings with respect to clarifications and non-conformities and the closure of the findings, as appropriate and preparing a draft verification opinion based on the auditing findings and conclusions

·       Technical review of the draft verification opinion along with other documents as appropriate by an independent competent technical review team

·       Finalization of the verification opinion (this report)

 

Earthood Services Private Limited (ESPL) has verified and hereby certifies that the GCC project activity “Renewable Solar Power Project by Phelan Energy India RJ Private Limited”:

 

·       Has correctly described the Project Activity in the Project Submission Form (version 04 dated: 26/05/2023) including the applicability of the approved methodology ACM0002 Version 21.0 and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively;

·       Is likely to generate GHG emission reductions amounting to the estimated 112,250 tCO2e/yr as indicated in the PSF /07/, which are additional to the reductions that are likely to occur in absence of the Project Activity and complies with all applicable GCC rules, including ISO 14064-2 and ISO 14064-3, and therefore requests the GCC Program to register the Project Activity;

·       Is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental Nonet-harm Label (E+) and the Social No-net-harm Label (S+); and

·       Is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 3 SDGs, which is likely to achieve the silver SDG certification label (SDG+)

Report (Public) Verification Report (public)
Verification report date
First Request for Registration Date 2023-07-25