PROJECT DETAILS

Project Submission No. S00326
Project Title 50 MW Solar Power Project in Kasargod, Kerala
Project Owner (as per PSF & LOA) Indian Renewable Energy Development Agency Ltd
Submission Date 4 Jul 2022
Global Stakeholder Consultation Period 31 Aug 2022 - 14 Sep 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version GCCM001 - Methodology for Renewable Energy Generation Projects Supplying Electricity to Grid or Captive Consumers, version 3.0
Forecasted GHG Emission Reduction (tCO2e/Year) 71,541 (tCO2e/Year)
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Gold
Forecasted Market Eligibility CORSIA(C+)
Country India
Focal Point of Project Owners (FP)
Saurabh Garg
Email of Contact Person of FP (Primary) saurabh@ireda.in
Email of Contact Person of FP (Secondary) mshowkatali@ireda.in
Email-id of External representative saurabh@ireda.in
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

The purpose of the project activity is to generate clean electricity  by harnessing the renewable “Solar Energy” with the help of Solar PV technology.

This is a greenfield 50 MWac Solar power plant being implemented in Kasargod, Kerala  of India by Indian Renewaable Energy Development Agency Ltd. The electricity generated by the project “50 MW Solar Power Project in Kasargod, Kerala” will thus replace the equivalent amount of electricity generated by the operation of existing grid connected power plants (mostly fossil fuel-based power plants).

Additional Information

 The estimated annual average electricity generation by the project activity 76,885 MWh and the estimated annual average GHG emission reductions by the project activity is 71,541 tCO2e.