PROJECT DETAILS

Project Submission No. S00666
Project Title 30 MW (AC) GRID CONNECTED SOLAR PV PROJECT UNDER SECI BY BHAGERIA INDUSTRIES LIMITED
Project Owner (as per PSF & LOA) BHAGERIA INDUSTRIES LIMITED
Submission Date 4 Jul 2022
Global Stakeholder Consultation Period 5 Dec 2022 - 19 Dec 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version ACM0002, Version 21.0
Forecasted GHG Emission Reduction (tCO2e/Year) 53,563 (tCO2e/Year)
Verified GHG Emission Reduction (tCO2e/Year) (tCO2e/Year)
Forecasted E+ Label Yes
Verified E+ Label
Forecasted S+ Label Yes
Verified S+ Label
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Gold
Verified SDG+ Label
Forecasted Market Eligibility CORSIA(C+)
Verified Market Eligibility
Country India
Focal Point of Project Owners (FP)
Bhageria Industries Limited
Email of Contact Person of FP (Primary) vikas.gh@bhageriagroup.com
Email of Contact Person of FP (Secondary) ho.solar@bhageriagroup.com
Name of Authorized External Representative Organization NA
Name of Focal Point of External Representative NA
Email-id of External representative vikas.gh@bhageriagroup.com
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

The main purpose of this project activity is to generate clean form of electricity through renewable solar energy source.
Bhageria Industries Ltd. is the promoter of the proposed project activity which involves installation of 30 MW solar power
project at village- Kombhalne, Tehsil- Akole, District- Ahmednagar, Maharashtra. The solar power project is installed in
the state of Maharashtra in India by Bhageria Industries Ltd, at site where no renewable/solar power plant was operating
prior to the implementation of the project activity (green-field power plant).The electricity generated from solar power
plant is exported to the Indian grid, thus replaces equivalent amount of electricity generated from the operation of
existing grid connected power plants which is mainly dominated by thermal/fossil fuel-based power plant. The project
activity thus reduces the anthropogenic emissions of greenhouse gases (GHGs) associated with equivalent amount of
electricity generation from the existing grid connected power plants (mostly fossil fuel based) and from addition of new generation sources into the grid.

Additional Information
VERIFICATION OUTCOME
Opinion

TUV SUD South Asia Pvt. Ltd. was contracted by Bhageria Industries Ltd for project verification of the project activity “30 MW (AC) Grid connected Solar PV Project under SECI by Bhageria Industries Limited” in India. The project verification was performed based on rules and requirements defined by GCC for the project activity.
The project activity is a wind power project, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved baseline and ACM0002 Grid-connected electricity generation from renewable sources, Version 21.0 and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard, Project-Sustainability-Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms.
The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 53,563 tCO2e/year over the 10 years crediting period starting from 17/06/2017.TUV SUD has informed the project owners of the project verification outcome through the draft project verification report and final project verification report. The final project verification report contains the information with regard to fulfilment of the requirements for project verification, as appropriate.
TUV SUD applied the following verification process and methodology using a competent verification team;
• The desk review of documents and evidence submitted by the project owner in context of the reference GCC rules and guidelines issued,
• Undertaking/conducting site visit, interview, or interactions with the representative of the project owner
• Reporting audit findings with respect to clarifications and non-conformities and the closure of the findings, as appropriate
• Preparing a draft verification opinion based on the auditing findings and conclusions
• Technical review of the draft project verification opinion along with other documents as appropriate by an independent competent technical review team.
• Finalization of the project verification opinion (this report)
TUV SUD South Asia Private Limited (TUV SUD) has verified and hereby certifies that the GCC project activity “30 MW (AC) Grid connected Solar PV Project under SECI by Bhageria Industries Limited” in India.
a. Has correctly described the Project Activity in the Project Submission Form including the applicability of the approved methodology ACM0002 Grid-connected electricity generation from renewable sources, Version 21.0 and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively.
b. Is likely to generate GHG emission reductions amounting to the estimated 535,632 tCO2e as indicated in the PSF, which are additional to the reductions that are likely to occur in absence of the Project Activity and complies with all applicable GCC rules, including ISO 14064-2 and ISO 14064-3, and therefore requests the GCC Program to register the Project Activity;
c. is not likely to cause any net-harm to the environment and/or society and complies with the environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental Nonet-harm Label (E+) and the Social No net-harm Label (S+); and d. is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 4 SDGs, which is likely to achieve the Gold SDG certification label (SDG+).

Report (Public) Verification Report (public)
Verification report date 2023-12-05
First Request for Registration Date 2023-12-06