IMPORTANT UPDATE: We are migrating to GCC 2.0. We have restricted new projects registration and further updates to migrated project. Please visit to GCC 2.0.

PROJECT DETAILS

Project Submission No. S00599
Project Title Sichuan Gashe Longdong Hydropower Station
Project Owner(s) (as per PSF & LOA) Sichuan Juneng Intelligent Network Energy Tech Co., Ltd.
Submission Date 2022-07-03
Global Stakeholder Consultation Period 2022-11-15 to
2022-11-29
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Hydro Power
GCC/CDM Methodology & Version ACM0002: Grid-connected electricity generation from renewable sources --- Version 20.0
Forecasted GHG Emission Reduction (tCO2e/Year) 395,245
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Gold
Forecasted Market Eligibility C+ - Pilot Phase
Country
 China
Focal Point of Project Owners
Sichuan Juneng Intelligent Network Energy Tech Co., Ltd
Email of Contact Person of FP (Primary) eric.zhou8@hotmail.com
Email of Contact Person of FP (Secondary) 18459470@qq.com
Name of Authorized External Representative Organization Goldchina Consultancy International Co., Ltd.
Name of Focal Point of External Representative Zheng Zhaoning
Email-id of External representative zzn@gcci-carbon.com
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

The project installed three generators with a total installed capacity of 165MW. The total surface area of the reservoir at full capacity is 37,100m2 and the power density of the project is 4,447W/m2. The electricity supplied to the grid is estimated to be 690,930MWh, corresponding to the annual ACCs of 395,245tCO2e. The total ACCs in the fixed 10 years crediting period is 3,952,450tCO2e.