| Project Submission No. | S00964 |
|---|---|
| Project Title | New GCC Thuan Hoa Hydropower 38MW |
| Project Owner(s) (as per PSF & LOA) | EKI Energy Services Limited |
| Submission Date | 2022-07-03 |
| Global Stakeholder Consultation Period |
2023-04-18 to 2023-05-02 |
| Sector | 1.Energy industries (renewable-/non-renewable sources) |
| Project Type | Hydro Power |
| GCC/CDM Methodology & Version | ACM0002 Grid-connected electricity generation from renewable sources - Version 21.0 |
| Forecasted GHG Emission Reduction (tCO2e/Year) |
|
| Forecasted E+ Label | Yes |
| Forecasted S+ Label | Yes |
| Forecasted SDG+ Goals |
|
| Forecasted SDG+ Label | Platinum |
| Forecasted Market Eligibility | C+ - Pilot Phase |
| Country |
Viet Nam
|
|---|---|
|
Focal Point of Project Owners
|
EKI Energy Services Limited |
| Email of Contact Person of FP (Primary) | manish@enkingint.org |
| Email of Contact Person of FP (Secondary) | naveen@enkingint.org |
| Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
| Project Brief | The Project Activity is the installation of a new grid-connected 38 MW Hydro power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project is built on Song Lo River, in Lung Pu Village, Thuan Hoa Ward, Vi Xuyen District, Ha Giang Province, Vietnam. The estimated annual power generation is 127,942 MWh. |
|---|---|
| Additional Information | The annual emission calculation for this project activity is 102,877 TCO2e. |