Project Submission No. | S00612 |
---|---|
Project Title | SERTAO and SOBRAL I Solar PV Project by GPG NATURGY |
Project Owner(s) (as per PSF & LOA) | NATURGY COMMODITIES TRADING S.A. |
Submission Date | 2022-07-03 |
Global Stakeholder Consultation Period |
2022-11-20 to 2022-12-04 |
Registration Date | 2024-08-03 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
Project Type | Solar Power |
GCC/CDM Methodology & Version | ACM0002 Grid-connected electricity generation from renewable sources, ver 21.0 |
Forecasted GHG Emission Reduction (tCO2e/Year) | 44,924 |
Verified GHG Emission Reduction (tCO2e/Year) | 44,924 |
Forecasted E+ Label | Yes |
Verified E+ Label | Yes |
Forecasted S+ Label | Yes |
Verified S+ Label | Yes |
Forecasted SDG+ Goals | |
Verified SDG+ Goals | |
Forecasted SDG+ Label | Platinum |
Verified SDG+ Label | Platinum |
Forecasted Market Eligibility | C+ - Pilot Phase |
Verified Market Eligibility | C+ - Pilot Phase |
Location Details
Open Full Map
|
|
Country |
Brazil
|
---|---|
Focal Point of Project Owners
|
Naturgy Commodities Trading |
Email of Contact Person of FP (Primary) | greentrading@naturgy.com |
Email of Contact Person of FP (Secondary) | cgomezb@naturgy.com |
Project Verifier | Carbon Check (India) Private Limited |
Documents for Global Stakeholder Consultation | Project Submision
Calculation Sheet Other Documents |
Request For Registration Documents | Verified Project Submision
Verified Calculation Sheet Other Verified Documents |
Request for Registration Form | Registration Form |
Project Brief | The project activity is to generate electricity by harnessing the solar energy by using the solar photovoltaic technology and thereby feed the generated electricity to the Brazilian national grid. |
---|
Report (Public) | Verification Report (public) |
---|---|
Verification report date | 2024-08-01 |
First Request for Registration Date | 2023-10-30 |
Opinion |
CCIPL was contracted by SERTAO I SOLAR ENERGIA SPE S.A on 27/01/2023, for project verification of the project activity “SERTAO and SOBRAL I Solar PV Project by GPG NATURGY”. The project verification was performed based on rules and requirements defined by GCC for the project activity. The project activity is a solar power project, which results in reductions of CO2e emissions that are real, measurable and give long-term benefits to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved baseline and monitoring ACM0002 “Grid-connected electricity generation from renewable sources”, Version 21.0 and is assessed against latest valid PS, VS and Environment and Social Safeguards Standard, Project-Sustainability-Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance/Forms. The project activity is likely to achieve the anticipated emission reductions stated in the PSF provided the underlying assumptions do not change. The expected emission reductions (annual average) from the project activity are estimated to be 44,924 tCO2e/year over the 10 years crediting period starting from 09/09/2017. CCIPL has informed the project owners of the project verification outcome through the draft project verification report and final project verification report. The final project verification report contains the information regarding fulfilment of the requirements for project verification, as appropriate. CCIPL applied the following verification process and methodology using a competent verification team. · The desk review of documents and evidence submitted by the project owner in context of the reference GCC rules and guidelines issued, · Undertaking/conducting site visit, interview, or interactions with the representative of the project owner. · Reporting audit findings with respect to clarifications and non-conformities and the closure of the findings, as appropriate · Preparing a draft verification opinion based on the auditing findings and conclusions. · Technical review of the draft project verification opinion along with other documents as appropriate by an independent competent technical review team. · Finalization of the project verification opinion (this report) Carbon Check (India) Private Ltd. (CCIPL) has verified and hereby certifies that the GCC project activity “SERTAO and SOBRAL I Solar PV Project by GPG NATURGY”. a. Has correctly described the Project Activity in the Project Submission Form including the applicability of the approved methodology ACM0002, version 21.0 and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively. b. Is likely to generate GHG emission reductions amounting to the estimated 449,240tCO2e for whole crediting period of 10 years as indicated in the PSF, which are additional to the reductions that are likely to occur in absence of the Project Activity and complies with all applicable GCC rules, including ISO 14064-2 and ISO 14064-3, and therefore requests the GCC Program to register the Project Activity. c. is not likely to cause any net-harm to the environment and/or society and complies with the environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental Nonet-harm Label (E+) and the Social No-net-harm Label (S+); and d. is likely to contribute to the achievement of United Nations Sustainable Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 5 SDGs, which is likely to achieve the platinum SDG certification label (SDG+) e. is likely to contribute to CORSIA Eligible Emission Units and has CORSIA Label (C+) certification valid till 31 December 2020. A written attestation from the Host country on double counting is not required until 31 December 2020 and the project was found meeting the applicable requirements prescribed by ICAO.
|