IMPORTANT UPDATE: We are migrating to GCC 2.0. We have restricted new projects registration and further updates to migrated project. Please visit to GCC 2.0.

PROJECT DETAILS

Project Submission No. S00820
Project Title Solar Power Project in Andhra Pradesh, India
Project Owner(s) (as per PSF & LOA) Andhra Pradesh Power Generation Corporation Limited
Submission Date 2022-07-02
Global Stakeholder Consultation Period 2023-01-15 to
2023-01-29
Registration Date 2025-12-26
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version ACM0002 Methodology for Grid-connected electricity generation from renewable sources, version 21.0
Forecasted GHG Emission Reduction (tCO2e/Year) 600,673
Verified GHG Emission Reduction (tCO2e/Year) 600,673
Forecasted E+ Label Yes
Verified E+ Label Yes
Forecasted S+ Label Yes
Verified S+ Label Yes
Forecasted SDG+ Goals
Verified SDG+ Goals
Forecasted SDG+ Label Silver
Verified SDG+ Label Silver
Forecasted Market Eligibility C+ - Pilot Phase
Verified Market Eligibility C+ - Pilot Phase
Location Details Open Full Map
Country
 India
Focal Point of Project Owners
Andhra Pradesh Power Generation Corporation Limited
Email of Contact Person of FP (Primary) ce-comml@apgenco.gov.in
Email of Contact Person of FP (Secondary) cecommlapgenco@gmail.com
Project Verifier LGAI TECHNOLOGICAL CENTER, S.A.
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Request For Registration Documents Verified Project Submision
Verified Calculation Sheet

Other Verified Documents
Request for Registration Form Registration Form
Project Brief

The project activity is the installation of a new grid-connected 400 MWAC Solar power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). Earlier the project was proposed for 500MW but at later stage the bids was finalized for three bidders and the Letters of Intent (LoI) were issued to the three firms viz. (i) M/s Vikram Solar Pvt. Ltd. for 200 MW, (ii) M/s KEC for 100 MW and (iii) M/s MCNally Bharat for 100 MW, on 09/03/2017 for executing the solar power project of 400 MW capacity and that the detailed contracts were issued on 02/05/2017. The project activity is solar power project which is being implemented in Anantapur, Andhra Pradesh by Andhra Pradesh Power Generation Corporation Limited. The electricity generated from Project Activity is exported to the Indian grid there by displacing the consumption of electricity from the regional grid electricity distribution system.

The electricity generated by the project “Solar Power Project in Andhra Pradesh, India” will thus replace the equivalent amount of electricity generated by the operation of existing grid connected power plants (mostly fossil fuel-based power plants). In this scope, Andhra Pradesh Power Generation Corporation Limited planned to install Solar Panels in with the purpose of contributing to the national economy. The estimated annual average electricity generation by the project activity is 645,175 MWh.

Additional Information

The  project activity will replace anthropogenic emissions of greenhouse gases (GHG’s) estimated to be a total of 6,006,731 tCO2e over the total 10 years crediting period or average 600,673 tCO2e/annum, thereon displacing 6,451,752 MWh amount of electricity over the 10-year crediting period or average of 645,175 MWh/year amount of electricity from the generation-mix of power plants connected to the Indian electricity grid, which is mainly dominated by thermal/ fossil fuel-based power plant.

VERIFICATION OUTCOME
Report (Public) Verification Report (public)
Verification report date 2025-12-24
First Request for Registration Date 2024-01-14
Opinion

LGAI Technological Center S.A. (Applus+ Certification) has performed a verification of the “Solar Power Project in Andhra Pradesh, India”. The verification is performed on the basis of GCC criteria project verification standard, Version 3.1 for the project activity, GCC guideline and host country criteria, as well as criteria given to provide for consistent project operations, monitoring and reporting.

The review of the final version of GCC PSF and the subsequent Onsite Audit/ follow-up interviews has provided Applus+ Certification with sufficient evidence to determine the fulfillment of stated criteria. In our opinion, the project meets all relevant GCC project standard requirements for the GCC. The project will hence be recommended by LGAI Technological Center S.A. (Applus+ Certification) for registration with the GCC.

By displacing fossil fuel-based electricity with electricity generated from a renewable source, the project results in reductions of CO2 emissions that are real, measurable and give long-term benefits to the mitigation of climate change. Emission reductions attributable to the project are hence additional to any that would occur in the absence of the project activity. Given that the project is implemented as designed, the project is likely to achieve the estimated amount of annual emission reductions of 600,673 tCO2e per year.

The verification has been performed following the requirements of the latest version of GCC verification standard, Version 03.1, GCC Project Standard, version 03.1 and on the basis of the contractual agreement.

In detail the conclusions can be summarized as follows:

-            Project Submission Form includes applicability of the approved methodology ACM0002, version 21.0 and meets the methodology applicability conditions, is additional and is expected to achieve the forecasted real measurable and additional GHG emission reductions, complies with the monitoring methodology, has appropriately conducted local and global stakeholder consultation processes and has calculated emission reduction estimates correctly and conservatively;

-            The project does not result in negative social, environmental and/or economic impacts.

-            The project contribution to Environment, Social Development and Economic and technological development

-            The project additionality is sufficiently justified in the GCC PSF.

-            Conservative assumptions were applied in the project description.

-            The monitoring plan of SDG parameters is transparent and adequate.

-            The project meets the local stakeholder consultation requirements.

      The conclusions of this report show, that the project, as it was described in the project documentation, is in line with all criteria applicable for the verification.

© 2026 Global Carbon Council