Project Submission No. | S00743 |
---|---|
Project Title | 12 MW Wind Energy Project in Mundra, Gujarat |
Project Owner (as per PSF & LOA) | Adani Green Energy Limited; Adani Renewable Energy (KA) Limited |
Focal Point of Project Owners*(FP)
|
Adani Green Energy Limited |
Email of Contact Person of FP (Primary) | emission.reductions@adani.com |
Email of Contact Person of FP (Secondary) | sandip.saha@adani.com |
Country | India |
Submission Date | 1 Jul 2022 |
Global Stakeholder Consultation Period | 20 Dec 2022 - 3 Jan 2023 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
GCC/CDM Methodology & Version | AMS-1. D- Grid connected renewable electricity Generation, Version -18 |
Forecasted GHG Emission Reduction(TCO2/Year) | 42,930 |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
---|---|
Forecasted SDG+ Goals | 3, 5, 7, 8, 9 & 13 |
Forecasted SDG+ Label | Diamond |
Forecasted Market Eligibility | CORSIA(C+) |
Name of Authorized External Representative Organization | |
Name of Focal Point of External Representative | |
Email-id of Focal Point | emission.reductions@adani.com |
Documents for Global Stakeholder Consultation | Project Submision, Calculation Sheet, Other Documents |
Project Brief | The proposed project activity is the installation of a new grid-connected 12 MW wind power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project activity is wind power project, which is being implemented in Kutch, Gujarat of India. The power generated from all the project activity is fed into the respective substation and Indian National Grid, thereby reducing greenhouse gas emission reduction into the atmosphere. The average power generation from the bundled project activity is 46,137.17 MWh and the emission reduction achieved is 42,930 tCO2/Annum. |
---|---|
Additional Information |