IMPORTANT UPDATE: We are migrating to GCC 2.0. We have restricted new projects registration and further updates to migrated project. Please visit to GCC 2.0.

PROJECT DETAILS

Project Submission No. S00950
Project Title Folha Larga Norte Renewable Energy Project
Project Owner(s) (as per PSF & LOA) EDF EN DO BRASIL PARTICIPAÇÕES LTDA.
Submission Date 2022-07-01
Global Stakeholder Consultation Period 2023-04-11 to
2023-04-25
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Wind Power
GCC/CDM Methodology & Version ACM0002 – Grid-connected electricity generation from renewable sources V21.0
Forecasted GHG Emission Reduction (tCO2e/Year) 445,330
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Diamond
Forecasted Market Eligibility C+ - Pilot Phase
Country
 Brazil
Focal Point of Project Owners
EDF EN DO BRASIL PARTICIPAÇÕES LTDA
Email of Contact Person of FP (Primary) comercial@edf-re.com.br
Email of Contact Person of FP (Secondary) backoffice@edf-re.com.br
Email-id of External representative comercial@edf-re.com.br
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

The proposed project activity consists in the implementation and operation of a new wind power electricity generation project named Folha Larga Norte. It is divided into two bundle projects, Folha Larga Phase 1 and Folha Larga Phase 2.
The Folha Larga Phase 1 wind farm comprises the projects Ventos de São Januário 01 Wind Farm, Ventos de São Januário 04 Wind Farm and Ventos de São Januário 14 Wind Farm, totaling an installed capacity of 105 MW.
The Folha Larga Phase 2 wind farm is made up of the Ventos de São Januário 03 Wind Farm, the Ventos de São Januário 05 Wind Farm, the Ventos de São Januário 06 Wind Farm, Ventos de São Januário 10 Wind Farm and Ventos de São Januário 11 Wind Farm, totaling an installed capacity of 197,4 MW.
Both areas are in the rural zone of the municipality of Campo Formoso, northern region of the State of Bahia, 428 km away from the capital Salvador.

The project activity will deliver approximately 1,562,151 MWh/year of renewable electricity to the National Interconnected System (Sistema Interligado Nacional - SIN). In the baseline scenario, electricity delivered to the grid by the project activity would have been generated by the operation of grid-connected power plants and by the addition of new generation sources, as reflected in the combined margin (CM) calculations. Hence, the project activity will promote GHG emissions reductions by displacing fossil fuel-based electricity generation that would otherwise occur.