PROJECT DETAILS

Project Submission No. S00962
Project Title 23 MW Waste Heat Recovery( WHRS)Project by UltraTech Nathdwara Cement Limited (Unit Nathdwara Cement works)
Project Owner(s) (as per PSF & LOA) UltraTech Cement Limited
Submission Date 2022-07-01
Global Stakeholder Consultation Period 2023-04-13 to
2023-04-27
Sector 4.Manufacturing industries
Project Type WHRS
GCC/CDM Methodology & Version ACM0012: Waste Energy Recovery-Version 6
Forecasted GHG Emission Reduction (tCO2e/Year) 104,455
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Gold
Forecasted Market Eligibility C+ - Pilot Phase
Country
 India
Focal Point of Project Owners
UltraTech Cement Limited
Email of Contact Person of FP (Primary) anand.bindal@adityabirla.com
Email of Contact Person of FP (Secondary) raj.narayanan@adityabirla.com
Name of Authorized External Representative Organization Infinite Environmental Solutions LLP
Name of Focal Point of External Representative Jimmy Sah
Email-id of External representative jimmy@infisolutions.org
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

Ultratech Nathdwara Cement Limited (UNCL) has a cement plant having clinker production line with the
design capacity of 6500 tons/per day, which can burn many forms of coal and coke in the kiln and in
the pre-calciner. The heat released from burning fossil fuel in the kiln and pre-calciner is used in the
clinkerization process. While most of the heat is used in the said processes, a substantial amount of
heat is lost through waste gases from the Preheater and AQC in the cement plant. The Cement plant
is located at Nathdwara, District Rajsamand of Rajashthan state of India.

Additional Information

The annual net electricity generation from WHRS plant amounts to 114,761MWh and yearly net emission reduction is 104,455 tCO2e. 

The estimated total CO2e emission reduction by the project activity over the fix crediting period of 10 years is expected to be 10,44,550  tCO2e.