PROJECT DETAILS

Project Submission No. S00906
Project Title Bundled Wind Power Project in Tamilnadu, coordinated by VEC-003
Project Owner (as per PSF & LOA) Ventus Energy Consultants
Focal Point of Project Owners*(FP)
Ventus Energy Consultants
Email of Contact Person of FP (Primary) bilateral@ventusindia.com
Email of Contact Person of FP (Secondary) sales@ventusindia.com
Country India
Submission Date 1 Jul 2022
Global Stakeholder Consultation Period 5 Mar 2023 - 19 Mar 2023
Sector 1.Energy industries (renewable-/non-renewable sources)
GCC/CDM Methodology & Version ACM0002: Grid-connected electricity generation from renewable sources --- Version 20.0
Forecasted GHG Emission Reduction(TCO2/Year) 46,473
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals 1,7,8,9,13
Forecasted SDG+ Label Platinum
Forecasted Market Eligibility CORSIA(C+)
Name of Authorized External Representative Organization
Name of Focal Point of External Representative
Email-id of Focal Point
Documents for Global Stakeholder Consultation Project Submision, Calculation Sheet, Other Documents
Project Brief

The proposed project activity is the installation of a new grid-connected group captive bundled 21 MW wind power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project is implemented in Tamilnadu state of India.


The project activity uses renewable energy (wind) as a clean fuel to generate electrical energy. The total installed capacity of the project is 21 MW, which comprises 10 nos. Wind Turbine Generators (WTGs) of capacity 2100 kW (manufacturer Suzlon).


The electricity generated by the Project Activity thus replaces the equivalent amount of electricity generated by the operation of existing/ grid connected power plants (mostly fossil fuel based power plants) and by addition of new generation sources into the grid. The Project Activity thus reduces the anthropogenic emissions of greenhouse gases (GHGs) in to the atmosphere associated with the equivalent amount of electricity generation from the existing grid connected power plants (mostly fossil fuel) and by addition of new generation sources into the grid.

Additional Information

The estimated emission reductions achieved for the entire crediting period of 10 years are 464,730 tCO2e/annum.