PROJECT DETAILS

Project Submission No. S00589
Project Title Huai'an Diliutun Phase I 20MW Solar Power Project
Project Owner (as per PSF & LOA) Beijing BOE Energy Technology Co., Ltd.
Submission Date 8 Jun 2022
Global Stakeholder Consultation Period 14 Nov 2022 - 28 Nov 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
Project Type Solar Power
GCC/CDM Methodology & Version ACM0002: Grid-connected electricity generation from renewable sources” (Version 20.0)
Forecasted GHG Emission Reduction (tCO2e/Year) 24,435 (tCO2e/Year)
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals
Forecasted SDG+ Label Gold
Forecasted Market Eligibility CORSIA(C+)
Location Details Open Full Map
Country China
Focal Point of Project Owners (FP)
Beijing BOE Energy Technology Co., Ltd.
Email of Contact Person of FP (Primary) zhangxiaomeng@boe.com.cn
Email of Contact Person of FP (Secondary) zhangxiaomeng@boe.com.cn
Documents for Global Stakeholder Consultation Project Submision
Calculation Sheet

Other Documents
Project Brief

Huai'an Diliutun Phase I 20MW Solar Power Project (hereafter referred to as “the project”) is a newly
built solar power project with total installation of 19.95MWp, consisting of 63838 PV modules. It is
developed by Hebei Huanda Trading Co., Ltd and located in Diliutun Town, Huai'an County, 
Zhangjiakou city, Hebei Province, China.
The purpose of the Project is to utilize the solar energy at the project site to generate and supply 
electricity to Northern China Power Grid (NCPG). The spatial extent of the project boundary includes 
the project power plant and all power plants connected physically to NCPG that the project is 
connected to.
Prior to the implementation of the Project, the electricity delivered to the grid by the project activity 
would be generated by the operation of grid-connected power plants and by the addition of new 
generation sources into the NCPG. This is also the baseline scenario.
The Project is a renewable energy project and is expected to supply an annual average of 
29,551MWh of zero-emission electricity to NCPG during the fixed 10-year crediting period, which will 
replace power generation of those fossil fuel-fired power plants delivered to the NCPG under the 
baseline scenario. The project is expected to achieve a green-house gas emission reduction of 
24,435tCO2e annually. The total emission reductions during the fixed 10-year crediting period will be 
244,353tCO2e. 
The project is expected to contribute to 4 SDGs which are SDG 7, 8, 9,13.

Additional Information
VERIFICATION OUTCOME
Opinion

Verico SCE has undertaken the project verification of the proposed project «Huai'an Diliutun Phase I 20MW Solar Power Project » in P.R.China to be implemented by Project Owner “Beijing BOE Energy Technology Co., Ltd.,” based on the requirements defined by GCC program for the project activity, and other rules applicable to the project verification including the host country’s legislation and its specific requirements for sustainable development.

The purpose of the project is to build a solar PV project which results in reductions of GHG emissions of 24,435 tCO2e annually during the fixed 10 year crediting period to replace the electricity generated by fossil fuel dominated power grid in the host country. It is demonstrated that the project is not a likely baseline scenario and the emission reductions attributable to the project are, hence, additional to any that would occur in the absence of the project activity. The project correctly applies the approved baseline and monitoring ACM0002 version 21.0 and is assessed against latest valid Project Standard, Verification Standard and Environment and Social Safeguards Standard and/or other applicable GCC/CDM Decisions/Tools/Guidance.

To arrive at the final verification conclusions and opinion, verico SCE carried out desk reviews, background investigations and an remote audit mission, taking into account the sustainable development related regulations/laws in the host country and specific GCC rules/requirements as well as applicable CDM standards, in particular the approved methodology ACM0002, version 21.0.

Through the project verification process, the verification team identified five (5) corrective action requests and ten (10) clarification requests and one (1) forward action request. The Project Owner has taken actions to address the findings and submitted to verico SCE several sets of project document revisions resulting in a final Project Submission Form, version 2.1 dated 01 November 2023 substantiated by supporting evidence. All findings have been appropriately closed before the issuance of this project verification statement.

The verification team is of the opinion that the GCC project: «Huai'an Diliutun Phase I 20MW Solar Power Project» with the verified final version of Project Submission Form:

a.  is in accordance with all the relevant GCC program requirements as well as the host country’s national requirements and if implemented as designed, is likely to achieve the verified emission reduction estimations of 24,435 tCO2e annually, following the monitoring provisions fixed in the final documentation;

b.  is not likely to cause any net-harm to the environment and/or society and complies with the Environmental and Social Safeguards Standard, and therefore requests the GCC Program to register the Project Activity, which is likely to achieve the requirements of the Environmental Nonet-harm Label (E+ ) and the Social No-net-harm Label (S+ ); and

c.  is likely to contribute to the achievement of United Nations Sustainability Development Goals (SDGs), comply with the Project Sustainability Standard, and contribute to achieving a total of 4 SDGs (7.2, 8.5, 9.4 and 13.2), which is likely to achieve the Gold SDG certification label (SDG+).

The project meets all of the GCC Rules and criteria for CORSIA and the project owner has clarified the intent use of carbon credits for the pilot phase of CORSIA hence for carbon credits issued generated during 01/01/2016 to 31/12/2020, HCA is not required for CORSIA labelled credits.

Therefore, verico SCE hereby certifies that the Project Submission Form version  2.1 dated 01 November 2023 of the proposed GCC project «Huai'an Diliutun Phase I 20MW Solar Power Project» is in accordance with the above stated requirements.

Report (Public) Verification Report (public)
Verification report date 2023-11-06
First Request for Registration Date 2023-11-13