PROJECT DETAILS

Project Submission No. S00292
Project Title Renewable wind power project in India -1- 017
Project Owner (as per PSF & LOA) M/s ReNew Green Energy Solutions Private Limited
Focal Point of Project Owners*(FP)
M/s/ ReNew Green Energy Solutions Private Limited
Email of Contact Person of FP (Primary) nikunj.nangalia@renewpower.in
Email of Contact Person of FP (Secondary) prabhat@renewpower.in
Country India
Submission Date 1 Jun 2022
Global Stakeholder Consultation Period 7 Aug 2022 - 21 Aug 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
GCC/CDM Methodology & Version ACM0002 Grid-connected electricity generation from renewable sources - Version 20.0
Forecasted GHG Emission Reduction(TCO2/Year) 926,789
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals 1,5,7,8,13
Forecasted SDG+ Label Platinum
Forecasted Market Eligibility CORSIA(C+)
Name of Authorized External Representative Organization
Name of Focal Point of External Representative
Email-id of Focal Point
Documents for Global Stakeholder Consultation Project Submision, Calculation Sheet, Other Documents
Project Brief

The Project Activity is the installation of a new grid-connected 300 MW wind power plant/unit at a site where no renewable power plant was operating prior to the implementation of the project activity (green-field plant). The project is implemented in Karnataka state of India.

The electricity generated from Project Activity is exported to the Indian grid in India there by displacing electricity from the regional grid electricity distribution system generated by fossil fuel-based power plants.

Additional Information

The project shall result in replacing anthropogenic emissions of greenhouse gases (GHG’s) estimated to be approximately 926,789 tCO2/year, thereon displacing 996,012 MWh/ year amount of electricity from the grid.