Project Submission No. | S00161 |
---|---|
Project Title | Aliağa WPP Capacity Addition Project |
Project Owner (as per PSF & LOA) | Bergama RES Enerji Üretim A.Ş. |
Focal Point of Project Owners*(FP)
|
Bilgin Güç Santralleri Enerji Üretim A.Ş. |
Email of Contact Person of FP (Primary) | altug@bilgin.com.tr |
Email of Contact Person of FP (Secondary) | kadir.cosar@bilgin.com.tr |
Country | Türkiye |
Submission Date | 15 Mar 2022 |
Global Stakeholder Consultation Period | 7 Apr 2022 - 21 Apr 2022 |
Sector | 1.Energy industries (renewable-/non-renewable sources) |
GCC/CDM Methodology & Version | ACM0002: “Grid-connected electricity generation from renewable sources” (Version 20.0) |
Forecasted GHG Emission Reduction(TCO2/Year) | 71,531 |
Forecasted E+ Label | Yes |
Forecasted S+ Label | Yes |
---|---|
Forecasted SDG+ Goals | 4, 6, 7, 8, 9, 11 |
Forecasted SDG+ Label | Diamond |
Forecasted Market Eligibility | CORSIA(C+) |
Name of Authorized External Representative Organization | |
Name of Focal Point of External Representative | |
Email-id of Focal Point | |
Documents for Global Stakeholder Consultation | Project Submision, Calculation Sheet, Other Documents |
Project Brief | The Aliağa WPP Capacity Addition was built and developed by Bergama RES Enerji Üretim A.Ş. The project activity is in the Bergama and Aliağa districts of Turkey’s western İzmir province. The project activity involves the installation of 10 wind turbines, each with a capacity of 3,000 kW, making the total installed capacity addition to 30 MW. The project owner built 10 more turbines in 2016 and increased the 90 MW capacity of the existing Aliağa Wind Power Project (WPP) to 120 MW with the 30 MW capacity of the proposed project. The proposed project activity consists of only the capacity addition to the existing Aliağa WPP. The average energy generation per year is estimated to be 110,354 MWh. Consequently, the annual emission reductions are estimated to be 71,531 t CO2e per the applied methodology. It exports the generated electricity to the Turkish national grid with generation from wind power, thereby contributing to the Host Country’s electricity demand, energy diversification, and renewable energy development. The project activity contributes to 7 sustainable development goals (SDGs). |
---|---|
Additional Information |