PROJECT DETAILS

Project Submission No. S00537
Project Title Rice Husk Based Biomass Power Project by T.S. Power Plant Company Limited
Project Owner (as per PSF & LOA) 1. T.S. Power Plant Company Limited 2. Green and Blue Planet Solutions Company Limited
Focal Point of Project Owners*(FP)
Green & Blue Planet Solutions Co., Ltd.
Email of Contact Person of FP (Primary) cc@gb-planet.com
Email of Contact Person of FP (Secondary) nan.samadee@gb-planet.com
Country Thailand
Submission Date 1 Jul 2022
Global Stakeholder Consultation Period 23 Oct 2022 - 6 Nov 2022
Sector 1.Energy industries (renewable-/non-renewable sources)
GCC/CDM Methodology & Version ASM-I.D: Grid connected renewable electricity generation, Version 18.0
Forecasted GHG Emission Reduction(TCO2/Year) 26,784
Forecasted E+ Label Yes
Forecasted S+ Label Yes
Forecasted SDG+ Goals 5, 7, 8, and 9
Forecasted SDG+ Label Platinum
Forecasted Market Eligibility CORSIA(C+)
Name of Authorized External Representative Organization
Name of Focal Point of External Representative
Email-id of Focal Point cc@gb-planet.com
Documents for Global Stakeholder Consultation Project Submision, Calculation Sheet, Other Documents
Project Brief

The project activity includes the construction, installation, and operation of a grid connected 6 MW biomass power plant which was established by T.S. Power Plant Company Limited in Khlong Khlung district, Kamphaeng Phet province in Thailand. The project aims to contribute to reducing environmental pollution from biomass residues and use those wastes for clean power generation to the Thailand National Power Grid.

The annual generated energy is expected to be 47,520 MWh according to the T.S. power plant power operation license issued by the Board of Investment (BOI) and the project will be able to deliver a reduction in emissions of around 26,784  tCO2e (tons of carbon dioxide equivalent) per annum and 240,910  tons of CO2 for the whole 10-year crediting period.

Additional Information